Skip to Content

Project Milestones

Date Milestones
4/16/2010
  • Core HR requirements
  • GL requirements
  • AP/AR requirements
  • Purchasing requirements
  • All other Financials module requirements
  • All other HR module requirements
5/28/2010
  • Upgrade ISAS financial system – 9.0 to 9.1
  • Fit/Gap results documentation for HR
6/11/2010
  • Fit/Gap results documentation for Financials
8/20/2010
  • Stand up server environment for testing, training and production
9/10/2010
  • Finance solution configuration book complete
6/13/2011
  • Finance integration testing complete
7/9/2011
  • Finance performance testing complete
8/31/2011
  • Financials cutover accepted (CTTS and DIR)
9/2/2011
  • Financials cutover complete
9/30/2011
  • Post implementation support – Month 1
10/31/2011
  • Post implementation support – Month 2 and project closeout